Greenough River
Solar Farm

Location: Greenough | Stage: Operational

Quick facts

  • Operational capacity: 40 megawatts (MW)

  • Total solar panels: 450,000 (stages one and two)

  • Estimated total energy generated: 98 GWhr/Year

  • Solar farm land usage: 244 hectares (stages one and two)

  • Tracking: 10 MW fixed, 30 MW single axis tracking

Stage One

  • Completed 2012

  • 10 megawatts

  • 150,000 PV panels 

Stage 1 of the Greenough River Solar Farm

Stage Two

  • Completed 2020

  • 30 megawatts

  • 300,000 PV panels

Harnessing the sun

Western Australia, particularly the Mid West region, receives plenty of sunshine throughout most of the year. This makes it an exceptional location for solar generation.

How does a solar farm work?

  • Solar photovoltaic cells inside solar panels are mounted on racks which run in rows, across an area exposed to a large amount of sunlight.

  • As the sun hits those solar photovoltaic cells, electrons flow in a low voltage known as direct current (or DC) electricity.

  • This DC electricity flows from the solar panels through a network of underground cabling to a solar inverter.

  • The inverter transforms the DC into alternating current (AC).

  • The solar farm is connected to Western Power transmission network, where the AC can travel to power homes and businesses across the SWIS.

Solar tracking technology

As part of the Stage 2 expansion of the solar farm, an additional 300,000 solar panels were installed alongside the original 150,000. These panels operate on a NEXTracker single axis system, which rotates the panels to follow the sun to generate more power in the mornings and afternoon compared to fixed panels.

Construction and operations

The project is owned by Bright Energy Investments, with development and asset management led by Synergy Renewable Energy Developments (SynergyRED).

Construction was delivered by JUWI Renewable Energy Pty Ltd. Operations and maintenance is managed by NovaSource Power Services, with on-site maintenance undertaken by local technicians.

Greenough River Solar Farm

Greenough River Solar Farm is located across a collection of farming properties near Walkaway, approximately 50 kilometres south east of Geraldton. Built in two stages, with the first stage completed in 2012, Greenough River Solar Farm was the first utility-scale solar generation facility in Australia.

Greenough River Solar Farm takes advantage of strong solar resource in the region, providing a significant contribution of renewable energy to the South West Interconnected System (SWIS).